The Construction at Cedar Beach: So Far
June 2nd
June 25th: Work Began on the Ponds
July 10th: Pond work hits a fever pitch
July 16th: The Pathways are starting to be dug
July 23rd: Pond Work is Finished
August 4th: The Ponds are Refilled
August 17th: The trenches in the Old Fashioned Garden are filled, Work begins in Rose Garden
August 20th: Final Pathway created in the Old Fashioned Garden, Towers rise in the Rose Garden
August 25th: Trenches dug in the Rose Gardens
October 26th: All Rose Garden Work Finished
They have entered into new phases of construction down there now. The paving of the pathways around the reflecting ponds in nearly complete. I'll have a complete photo log and comment next week. There is alot more left to happen down there and I'll make sure to show it on here.